"If we come back 12 to 18 months from now, no matter who is sitting, the cost is going to be higher than it is today," Mayor John Gunter said at the council's Sept. 28 special meeting, as reported by the Cape Coral Breeze. That night the council moved ahead with water, sewer and irrigation assessments for the North 3 Utilities Extension Project. Sixteen days later it paused the project for a redesign.
Most of the coverage has treated the pause as a relief for property owners.
Construction has not started. The three resolutions the council passed in September were initial assessment resolutions, which are now scheduled for repeal.
| Date | What happened |
|---|---|
| March 12, 2025 | Council is presented with the Alternative 5 roadway design for North 3 |
| Sept. 28, 2026 | Council passes Resolutions 243-26, 244-26 and 245-26 after a 5–3 vote rejects a motion to delay |
| Oct. 14, 2026 | At a workshop, council reaches consensus to pause, redesign Alternative 5 and rebid |
| Oct. 19, 2026 | Homeowner information meeting canceled |
| Nov. 2, 2026 | Repeal of the three assessment resolutions scheduled for council |
| Nov. 3, 2026 | General election, with four council seats on the ballot |
The area covers about three square miles: Kismet Parkway to the north, Burnt Store Road to the east, Bonefish Canal to the south and Spreader Waterway to the west. The city counts roughly 1,900 improved parcels and 3,200 unimproved ones inside it. With that many vacant lots, a large share of the property changing hands here is land, and that's where an assessment can make up the biggest part of the total cost.
As of this post's publication on Oct. 29, the Nov. 2 vote has not happened. The Breeze reported that the Oct. 14 consensus is not final until council acts.
Before the pause, the estimated charge per equivalent parcel was $35,264 east of Burnt Store Road and $41,029 west of it, covering water, wastewater and irrigation. An equivalent parcel is 10,000 square feet, which the city calls the typical residential lot. The city's financial services director told council that 93.5% of parcels fall between one and two equivalent parcels, so oversized lots would be assessed more.
The gap between east and west comes from Alternative 5. That design would rebuild the roads west of Burnt Store with the pavement moved to the center, longer driveways, an asphalt multi-use path and intersection and bridge work, at $5,765 per equivalent parcel. A typical UEP road restoration costs $2,963.95 per equivalent parcel. Swapping one for the other brings the west-side figure from $41,029 to about $38,228. The Breeze quoted the city manager explaining that the assessment is a division problem, with project cost divided by the number of equivalent parcels.
Removing Alternative 5 shrinks the cost being divided. Rebidding could raise it. Councilmember Keith Long, who supported the redesign, said during the workshop, "The cost will increase," according to the Breeze's Oct. 15 report. In September, Gunter had warned that pushing the project back would make the current bids invalid and that "adding another $3,000 to $4,000 is a disservice." The mayor also said the roughly $3 million redesign cost should not go into the assessments.
No revised assessment roll has been released.
North 3 has no payment schedule yet. The closest model is North 1 East, whose final assessment resolutions were approved Nov. 19, 2025. These figures belong to North 1 East and are not North 3 numbers:
For rental investors, the assessment is only part of the cost.
The Breeze's Sept. 29 report listed these connection costs for North 3:
The city's general UEP FAQ lists the meter fee at $310, so check the current amount with the city before budgeting.
Contract terms are negotiable, and this post is general information, not legal, tax or financial advice. Confirm how any assessment applies to a specific property with a Florida real estate attorney, your closing agent or the City of Cape Coral.
Is the North 3 assessment canceled? No. Council reached consensus on Oct. 14 to pause, redesign Alternative 5 and rebid. Repeal of the three resolutions is on the Nov. 2 agenda, and the city plans to bring the redesigned project back later.
Does the old completion date still hold? The city's North 3 page still describes completion by the end of 2028. That schedule came before the decision to redesign and rebid, so it is no longer reliable.
If you own, are buying or are thinking about selling a home or lot inside the North 3 boundary, Uptown Property Services can help you keep track of the process as the city's next decisions come in.